Moving subMIT to 100 Gbit/sec all the way

by

Dave and with yellow fibre incoming.

Dave and Paul received the 100 Gbit/sec yellow fibres from IS&T (left with Dave) and our subMIT switch is plugged in using the pink fibre (right with Zhangqier). The switch went smoothly on Tuesday (February 24, 2023).

Qier with pink fibre arriving.

Subsequent testing revealed node-to-node network throughput between Building 24 and Bates of up to 88 Gbit/sec (11 Gbytes/sec), approaching the wire speed limit.